Steam turbine manufacturers typically take several months to manufacture a turbine, depending on its size and complexity. Standardized turbines may take 6–12 months, while larger, customized ones can take 18 months or more.
The process involves design, material sourcing, machining, assembly, and testing. Lead times vary based on manufacturer capacity and project specifics. Contact @ +91 8023151486 for a more accurate estimate.